Question about Test Configurations and Resources.

We want to split our testing up across multiple browsers and track results that way.

At first I thought using a test configuration would be the answer, but then I noticed that there are no reports generated on them. I think I need to create a seperate project for each browser type?

How do I tell that I tested 50% of the test cases on IE 6.0 and only 10% on IE 5.5


Keep in mind I have a matrix of 6 browsers and 3 server versions. So each test I run has to be done on 18 seperate combinations.

passmark
04-26-2006, 12:23 PM
Yes configurations was meant for this type of thing. However we assumed that if a single config failed then the entire test was a fail until all configurations passed.

If you need to assign a separate pass and fail to each browser type then you need a test for each browser type. You can't assign for example, 10 passes and 6 fails to a single test case.

Yes, a seperate project for each broswer type would work I think.

-----